Worked example

Eight 10 AWG THHN wires total 0.1688 in². That fits Schedule 40 and exceeds the Schedule 80 space. Schedule 80 reaches a quotient of 7.77, below the 7.8 needed to allow eight equal-size conductors.

Where a route uses different schedules or tight fittings, check the actual raceway sections that govern. A thicker-wall section may be required where subject to physical damage. Size the pull around the dimensions and installation conditions of that section.

Calculation method

  1. Choose the actual raceway

    Start with the type printed on the raceway. Schedule 40, Schedule 80, EMT and liquidtight of the same trade size have different inside areas.

  2. Add every object occupying space

    Use a separate row for each size or insulation. Use actual area for bare grounds, compact aluminum or dimensions that differ from the Table 5 entries.

  3. Read the area limit

    Chapter 9 Table 1 assigns 53% to one conductor, 31% to two, and 40% to three or more. The worksheet uses the tabulated in² limits and identifies the same-size rounding allowance in Note 7.

The graphic uses area-scaled circle placement as an illustration. Bends, pulling tension, conductor jamming, ampacity adjustment, short-nipple rules and the suitability of the raceway are separate design checks.

Common questions

Why does thicker Schedule 80 have less wire space?

The thicker wall takes up more of the same nominal trade size, leaving less internal area.

Can I average Schedule 40 and Schedule 80 areas along a run?

Check each portion of the route using its own area and occupancy. A constriction still governs even in a short section of a longer pull.

References